Some of the new black aluminium windows are being installed in replacement for the existing along with some of the new openings within the new extension. We are also breaking out the old concrete floor and the underfloor heating to replace it with a new concrete floor with an upgraded amount of insulation and a ‘A’ rated energy efficient underfloor heating system.

photo photo 3 photo 1

 


The first floor is now complete and the roof is in place ready for the application of the flat roofing system. The timber structure for the fascias is also complete and we are expecting the windows to arrive to site within the next few days.

Hull second floor done 01 Hull second floor done 02 Hull second floor done 03


The steelwork is in place and the blockwork has now started to be constructed to form the first floor master bedroom extension. The roof joists are in place and we are now organising the installation of the insulation and single ply roofing membrane.

Topper second floor 2 Topper second floor