The ground works have begun, Addis Construction from Keighley undertook the ground works package. A very tight and difficult site to work on as it is narrow and has an access road running up the side which is constantly in use. The strategy from Addis was to dig out the perimeter and then move the digger out to clear the middle of the site to finish the ground bearing slab.