The steel frame for the main living space has been delivered and installed in one very wet day. The client can now see the main living space volume. The blockwork has been taken up to dpc and the external site drainage has been installed.

Steel frame harrogate


The footings have been dug out and the concrete has been put into the holes ready for the next stage of the works which is blockwork up to dpc. Unfortunately we came across a lot of asbestos when removing some of the original piggery which needed to be removed by a specialist contractor this has caused some delays to the build programme and also additional costs.

Footings Harrogate 02 Footings Harrogate 01 Footings Harrogate 03


Work to convert and extend the existing piggery in this greenbelt site in Harrogate into a fully disabled compliant home has begun.

T534 the piggery sm